Make-or-Buy and Outsourcing Decisions
Relevant cost analysis for internal manufacturing versus external sourcing, factoring in scarce resources, unavoidable fixed costs, opportunity costs, and strategic non-financial risks.
Study Text & Technical Notes
Topic Overview & Scope
Relevant cost analysis for internal manufacturing versus external sourcing, factoring in scarce resources, unavoidable fixed costs, opportunity costs, and strategic non-financial risks.
Essential Examinable Concepts
Key principles and theoretical foundations tested in this topic.
Short-Term Make-or-Buy Decision Rule
If internal capacity is surplus/idle, make in-house if the incremental (variable + attributable fixed) cost to make is less than the external purchase price. If buy price is less than avoidable make costs, buy externally...
Make-or-Buy with a Bottleneck Resource
When internal production is constrained by a scarce resource, calculate: Extra Cost of Buying per Unit of Scarce Resource = (Buy Price - Variable Cost to Make) / Scarce Resource Units per Component. Buy externally those ...
Opportunity Costs in Make-or-Buy
If making a component consumes plant capacity that could otherwise be used to produce an alternative profitable product or be rented to a third party, the forgone contribution or rental income is an opportunity cost that...
Treatment of Apportioned General Overheads
General corporate overheads (e.g. head office rent, CEO salary) that are apportioned across departments are UNAVOIDABLE and will continue regardless of whether a component is made or bought. They are completely IRRELEVAN...
ACCA Examiner Tips & Common Pitfalls
In ACCA PM examinations, questions testing Make-or-Buy and Outsourcing Decisions require candidates to look beyond rote definitions and demonstrate applied critical reasoning. Common student pitfalls include confusing legal form with economic substance, omitting mandatory disclosure steps, and failing to justify calculations with standard references.
Topic Mastery Checklist
- Master core definitions and scope boundaries for Make-or-Buy and Outsourcing Decisions
- Memorize key computational workings, journal entries, or audit test procedures
- Be able to critique real-world scenarios against relevant professional standards
- Practice time-pressured CBE questions under 1.8 minutes per mark
Practice questions
Authentic CBE practice questions — work through them step-by-step or view the complete bank.
Epsilon Ltd produces part P-100 with the following unit cost breakdown: Direct Materials: $8 Direct Labour: $6 Variable Overheads: $3 Allocated General Fixed Overheads: $5 Total Absorption Cost: $22 An external supplier offers to supply 10,000 units of P-100 for $19 each. Epsilon has spare capacity and allocated overheads will not change. What is the financial effect of buying part P-100 externally?
Show answer and explanation
Answer: Profits will decrease by $20,000
Relevant cost to make in-house = Direct Materials ($8) + Direct Labour ($6) + Variable Overheads ($3) = $17 per unit. Allocated fixed overheads ($5) are unavoidable and irrelevant. External buy price = $19 per unit. Buying externally costs an extra $19 - $17 = $2 per unit. For 10,000 units, company profit will decrease by $20,000.
Common traps: Option 2 compares the buy price ($19) with the full absorption cost ($22), falsely concluding a $3 profit increase ($30,000). Allocated overheads do not disappear when buying externally!
Sources: ACCA PM Study Text Chapter 10; ACCA PM Syllabus B2(a)
Exam traps for this topic
All PM exam tipsFlashcards & Key Terms
Active recall with 3D interactive flip deck or full term list.
All PM chapters
- 1. Activity-Based Costing (ABC)
- 2. Target Costing
- 3. Life-Cycle Costing
- 4. Throughput Accounting and Theory of Constraints
- 5. Environmental Management Accounting (EMA)
- 6. Limiting Factor Analysis
- 7. Linear Programming: Graphical Method
- 8. Linear Programming: Shadow Prices and Simplex Principles
- 9. Pricing Decisions
- 10. Make-or-Buy and Outsourcing Decisions
- 11. Shutdown and Discontinuation Decisions
- 12. Decision-Making under Risk and Uncertainty
- 13. Budgetary Systems and Motivation
- 14. Types of Budgetary Systems
- 15. Quantitative Forecasting and Learning Curves
- 16. Basic Variances Revisited
- 17. Material Mix and Yield Variances
- 18. Sales Mix and Quantity Variances
- 19. Planning and Operational Variances
- 20. Performance Management Information Systems
- 21. Financial Performance Measures
- 22. Non-Financial Performance and Divisional Control
Choosing a qualification? CPA vs ACCA 2026