Under the COSO ERM framework, which of the following represents the risk remaining after management has implemented internal controls and mitigation strategies?
Show answer and explanation
Answer: Residual risk
Residual risk is the risk that remains after management has taken action to mitigate risk, such as implementing internal controls or purchasing insurance.
Common traps: Inherent risk is the raw risk before any mitigation. Systemic risk affects an entire industry or market.
Sources: COSO ERM Framework; Gleim CIA Part 1, SU 7.1
- Question 1 of 8Single choice · 1 mark
Under the COSO ERM framework, which of the following represents the risk remaining after management has implemented internal controls and mitigation strategies?
Show answer and explanation
Answer: Residual risk
Residual risk is the risk that remains after management has taken action to mitigate risk, such as implementing internal controls or purchasing insurance.
Common traps: Inherent risk is the raw risk before any mitigation. Systemic risk affects an entire industry or market.
Sources: COSO ERM Framework; Gleim CIA Part 1, SU 7.1
- Question 2 of 8Single choice · 1 mark
A corporation decides to cancel the development of a speculative overseas chemical processing plant because the environmental and political hazards exceed what the board is willing to bear. Which risk response strategy was chosen?
Show answer and explanation
Answer: Risk avoidance
Risk avoidance involves exiting or halting the activity that gives rise to the risk entirely.
Common traps: Sharing transfers part of the risk (e.g. joint venture or insurance). Reduction applies controls. Acceptance absorbs the risk without altering the activity.
Sources: COSO ERM Framework; Gleim CIA Part 1, SU 7.3
- Question 3 of 8Single choice · 1 mark
Which of the following is one of the five core components of the 2017 COSO Enterprise Risk Management (ERM) framework?
Show answer and explanation
Answer: Strategy and Objective-Setting
The 5 components of COSO ERM 2017 are: (1) Governance and Culture, (2) Strategy and Objective-Setting, (3) Performance, (4) Review and Revision, and (5) Information, Communication, and Reporting.
Common traps: Control Activities is a component of the COSO Internal Control framework, not the ERM framework. Cost accounting and substantive testing are operational and audit procedures.
Sources: COSO ERM Framework (2017); Gleim CIA Part 1, SU 7.2
- Question 4 of 8Single choice · 1 mark
What is the key distinction between risk appetite and risk tolerance?
Show answer and explanation
Answer: Risk appetite represents the broad level of risk an entity is willing to accept to pursue its strategy, while risk tolerance reflects the acceptable variation in performance regarding specific objectives.
Risk appetite is broad and strategic (what types and amounts of risk the organization wants). Risk tolerance is tactical and measurable (acceptable variance around specific target performance).
Common traps: Neither is set by auditors (both are management and board duties). Both can have qualitative and quantitative measures.
Sources: COSO ERM Framework; Gleim CIA Part 1, SU 7.2
- Question 5 of 8Single choice · 1 mark
According to the IIA Position Paper on ERM, which of the following is considered a legitimate internal audit consulting role, provided safeguards are in place?
Show answer and explanation
Answer: Facilitating identification and evaluation of risks across business units.
Internal auditors may champion ERM, facilitate risk workshops, and coach management on risk responses, provided management actively participates and retains ownership.
Common traps: Setting risk appetite, imposing processes, and owning risk decisions are forbidden roles that impair independence.
Sources: IIA Position Paper: The Role of Internal Auditing in ERM; Gleim CIA Part 1, SU 7.1
- Question 6 of 8Single choice · 1 mark
In risk assessment, how is the severity of an identified risk event typically evaluated?
Show answer and explanation
Answer: By assessing both the likelihood of occurrence and the impact (severity) if the event occurs.
Standard risk assessment evaluates risks along two primary dimensions: likelihood (probability of occurrence) and impact (magnitude of consequences).
Common traps: Staff ratios, company age, and spreadsheet counts are irrelevant to calculating risk severity.
Sources: COSO ERM Performance Component; Gleim CIA Part 1, SU 7.3
- Question 7 of 8Single choice · 1 mark
An airline enters into derivative fuel hedging contracts to protect against price volatility in jet fuel. This risk response is classified as:
Show answer and explanation
Answer: Risk sharing / transfer
Financial hedging contracts, like insurance policies, transfer or share financial risk with market counterparties.
Common traps: Avoidance would mean stopping flying planes. Acceptance means absorbing price swings without hedging.
Sources: COSO ERM Framework; Gleim CIA Part 1, SU 7.3
- Question 8 of 8Single choice · 1 mark
Under ISO 31000, what is the central purpose of risk management?
Show answer and explanation
Answer: The creation and protection of value.
ISO 31000 states that the main purpose of risk management is the creation and protection of value. It improves performance, encourages innovation, and supports achievement of objectives.
Common traps: Zero uncertainty is impossible. Risk management enables prudent risk-taking, not stagnation or punitive audits.
Sources: ISO 31000:2018 Principles; Gleim CIA Part 1, SU 7.4
Exam traps for this topic
All P1 exam tips- Commonly confusedWhat is the difference between inherent risk, target residual risk, and actual residual risk?
- Commonly confusedHow does risk appetite differ from risk tolerance in enterprise risk management?
- Commonly confusedWhat are the primary differences between COSO ERM and ISO 31000 risk management frameworks?
- Exam trapCan internal audit establish risk management processes if management has none?
- Exam trapWho holds ultimate operational responsibility for managing organizational risks day-to-day?
- Commonly confusedWhat is the difference between first-line and second-line roles in the IIA Three Lines Model?
- Commonly confusedWhat is the difference between risk sharing (transfer) and risk reduction (mitigation)?
Flashcards & Key Terms
Active recall with 3D interactive flip deck or full term list.
Keyboard: Space or Enter flip · ← → move
Enterprise Risk Management (ERM)
The culture, capabilities, and practices, integrated with strategy-setting and its performance, that organizations rely on to manage risk in creating, preserving, and realizing value.
Example: Incorporating geopolitical and supply chain risk analyses into corporate 5-year strategic planning.
Source: COSO ERM Framework (2017)
5 Components of COSO ERM
1. Governance and Culture, 2. Strategy and Objective-Setting, 3. Performance, 4. Review and Revision, 5. Information, Communication, and Reporting.
Example: The 5 interconnected components supported by 20 underlying principles.
Source: COSO ERM Framework (2017)
Risk Appetite
The types and amount of risk, on a broad level, an organization is willing to accept in pursuit of value creation.
Example: A technology startup with a high risk appetite for disruptive R&D but zero appetite for regulatory noncompliance.
Source: COSO ERM Framework
Risk Tolerance
The boundaries of acceptable variation in performance related to achieving specific business objectives.
Example: Target delivery within 24 hours, with an acceptable variation of +/- 2 hours.
Source: COSO ERM Framework
Inherent Risk vs. Residual Risk
Inherent risk is the risk to an entity in the absence of any direct management action to alter its severity. Residual risk is the risk remaining after management has responded to the risk (implemented controls).
Example: Inherent cyber risk is extreme; after firewalls, MFA, and monitoring, residual risk is acceptable.
Source: Gleim CIA Part 1, SU 7.1
Risk Responses (5 Categories)
Accept (retain risk), Avoid (exit activity), Pursue (exploit risk for reward), Reduce/Mitigate (implement controls), Share/Transfer (insurance, hedging, outsourcing).
Example: Buying property fire insurance is a risk sharing response.
Source: COSO ERM Framework: Performance Component
ISO 31000 Framework
International risk management standard organized into three main pillars: Principles (creating value), Framework (leadership and commitment), and Process (communication, scope, assessment, treatment, monitoring).
Example: Applying ISO 31000 guidelines across global operations to harmonize risk vernacular.
Source: ISO 31000:2018
Risk Capacity
The maximum amount of risk an organization can absorb before violating regulatory constraints or threatening its existential survival.
Example: A bank's statutory capital reserves dictate its maximum risk capacity for loan defaults.
Source: COSO ERM Framework
What is risk management?
Risk management is a systematic series of activities for recognizing, evaluating, managing, and regulating potential situations or events to provide reasonable assurance that an entity can achieve its objectives. It balances potential negative impacts against opportunities while minimizing unexpected operational issues.
Example: An internal auditor evaluates whether the enterprise risk management team systematically identifies supply chain disruptions before expanding production.
Source: Subunit 7.1 Risk Management Processes, Standard 9.1
How does Standard 9.1 define the CAE's risk management duties?
Standard 9.1 requires the Chief Audit Executive to understand the organization's governance, risk management, and control processes to formulate an effective internal audit strategy and plan. The CAE gathers insights by reviewing meeting minutes, interviewing executive leadership, and examining prior assurance assessments.
Example: The CAE conducts structured interviews with board members to assess how executive leadership identifies operational risk exposures.
Source: Subunit 7.1 Risk Management Processes, Standard 9.1
The 5 Steps of the Risk Management Cycle
The risk management process consists of five sequential steps: identification of context, risk identification, risk assessment and prioritization, risk response selection, and continuous risk monitoring. Each step ensures risks are evaluated across all organizational levels relative to business objectives.
Example: An auditor verifies that a business unit established regulatory context before attempting to identify operational risk scenarios.
Source: Subunit 7.1 Risk Management Processes
Identification of Context in Risk Management
Establishing the preconditions and operational environments—such as applicable laws, capital projects, technology platforms, and market factors—within which risks must be managed. It ensures risk identification aligns with specific business realities.
Example: Prior to auditing a foreign branch, auditors evaluate local currency fluctuations and regulatory requirements as key contextual factors.
Source: Subunit 7.1 Risk Management Processes
Risk Assessment and Prioritization Phase
A three-part evaluation where management assesses the significance of an event, determines its likelihood of occurrence, and considers available mitigation controls. Qualitative or quantitative techniques like risk maps and risk rankings are used to prioritize resource allocation.
Example: Internal audit reviews a division's risk map to verify that high-impact, high-likelihood operational threats are prioritized for mitigation.
Source: Subunit 7.1 Risk Management Processes
Continuous Risk Monitoring and Key Information Sources
Ongoing evaluation of risk response effectiveness and evolving threat landscapes, relying on operational managers closest to daily activities and objective internal auditors. Monitoring ensures control failures or emerging risks are promptly identified.
Example: An internal auditor performs quarterly reviews of access log controls to verify that IT risk mitigations remain effective over time.
Source: Subunit 7.1 Risk Management Processes
Roles of the Board vs. Management in Risk Management
The board performs an oversight role by confirming that adequate and effective risk management processes exist, whereas senior management holds operational responsibility for designing and executing sound risk management practices.
Example: The audit committee reviews the annual enterprise risk report while executive leadership implements daily fraud prevention controls.
Source: Subunit 7.1 Risk Management Processes
Internal Audit Roles and Safeguards in Risk Management
Internal audit evaluates risk management effectiveness, recommends control improvements, and provides advisory insights, but must avoid assuming management operational responsibilities to maintain independence. If formal risk processes are absent, the CAE discusses risk oversight obligations with the board.
Example: The CAE advises management on control design for a new software tool while declining to make final operational selection decisions.
Source: Subunit 7.1 Risk Management Processes
Application of the Three Lines Model in Risk Management
The Three Lines Model structures governance into first line roles that directly manage operational risks, second line roles that provide risk expertise and oversight, and third line internal audit that delivers independent assurance to the board.
Example: Production line supervisors own day-to-day safety risks (first line), safety officers monitor compliance (second line), and auditors independently test safety controls (third line).
Source: Subunit 7.1 Risk Management Processes, Principle 1
What is Enterprise Risk Management (ERM) under COSO?
COSO ERM is defined as the culture, capabilities, and practices integrated with strategy-setting and performance that organizations rely on to manage risk in creating, preserving, and realizing stakeholder value. It aligns risk management across all organizational levels.
Example: Executive management utilizes the COSO ERM framework to integrate cyber risk assessments into its strategic decision-making for digital expansion.
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
Culture, Capabilities, and Practices in ERM
Culture encompasses attitudes and risk understandings reflecting mission, vision, and core values; capabilities represent the skills needed to execute goals; and practices are the collective methods used to manage risk across an entity.
Example: An auditor evaluates whether employee training programs build necessary risk assessment capabilities aligned with corporate core values.
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
Distinguishing Mission, Vision, and Core Values
Mission represents the organization's core purpose, vision defines its long-term aspirations, and core values establish essential beliefs regarding acceptable or unacceptable behaviors. Strategy communicates how the entity will achieve its mission and vision while honoring its core values.
Example: An internal audit engagement confirms that new operational business objectives support the company's stated mission of environmental sustainability.
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
What is risk appetite?
Risk appetite is the broad types and aggregate amount of risk an organization is prepared to accept in pursuit of value and strategic business objectives. It is established by management, approved by the board, and communicated throughout the entity.
Example: The board formally approves a conservative risk appetite statement that prohibits speculative investments in unverified foreign currencies.
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
What is risk tolerance?
Risk tolerance represents the acceptable variation in performance relative to achieving specific business objectives. It operationalizes risk appetite by providing practical boundaries for day-to-day operations.
Example: A logistics unit establishes a risk tolerance permitting no more than a 2% variance from target delivery schedules.
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
Risk Profile vs. Portfolio View
A risk profile is a composite view of risks related to a specific strategy, division, or business objective, whereas a portfolio view is a top-level composite view of risks across the entire entity and its overall strategy.
Example: The CAE examines individual division risk profiles to construct an enterprise-wide portfolio view of risk for the board.
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
Inherent Risk vs. Actual Residual Risk vs. Target Residual Risk
Inherent risk exists in the absence of any management action to alter severity; target residual risk is the risk level an entity prefers after planned management actions; and actual residual risk is the remaining risk after responses are executed.
Example: Management evaluates raw market volatility (inherent risk) and implements hedging controls to reduce remaining exposure (actual residual risk) down to acceptable levels (target residual risk).
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
Risk Inventory and Risk Capacity
Risk inventory consists of all identified risks affecting strategy and business objectives, while risk capacity is the maximum amount of risk an organization can physically or financially assume.
Example: An auditor checks whether total corporate debt exposure remains safely below the financial risk capacity established by the board.
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
ERM Roles of CEO, Board, and Risk Officer
The board provides ERM oversight, the CEO holds ultimate responsibility for strategy and ERM implementation, and a chief risk officer serves as a centralized coordinating point to facilitate risk management across the enterprise.
Example: The Chief Risk Officer consolidates risk reporting metrics from operational business units to present a unified report to the CEO and board.
Source: Subunit 7.2 COSO Framework -- Enterprise Risk Management (ERM) Overview
Five Interrelated Components of COSO ERM
The COSO ERM framework consists of five interrelated components containing 20 principles: Governance and Culture; Strategy and Objective Setting; Performance; Review and Revision; and Information, Communication, and Reporting.
Example: An audit team structures its enterprise risk management evaluation around the five core COSO ERM components.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
Governance and Culture Component Principles
This component sets organizational tone, establishes ERM responsibilities, and reflects desired risk behaviors through five principles: exercising board risk oversight, establishing operating structures, defining desired culture, demonstrating core values commitment, and retaining capable staff.
Example: Internal audit verifies that the board risk committee actively reviews executive succession plans to ensure leadership capabilities.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
Strategy and Objective Setting Component Principles
Focuses on aligning strategy with mission and core values through four principles: analyzing business context, defining risk appetite, evaluating alternative strategies, and establishing aligned business objectives.
Example: Auditors assess whether management conducted scenario analysis to evaluate risk profiles before choosing an acquisition strategy.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
Performance Component Principles in ERM
Concerns identifying, assessing, prioritizing, responding to, and developing a portfolio view of risks across five principles to support value-creation decisions.
Example: An auditor reviews the company's risk identification workshops to confirm emerging technology risks were properly documented.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
Qualitative vs. Quantitative Risk Assessment Methods
Qualitative methods (such as interviews and risk rankings) are efficient and less costly, whereas quantitative methods (such as decision trees, modeling, and Monte Carlo simulations) provide precise numerical estimates.
Example: Internal auditors use quantitative Monte Carlo simulations to model project cost overrun probabilities on major construction projects.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
The Five Categories of Risk Responses
Management responds to identified risks through five strategies: Acceptance (retention), Avoidance (eliminating the activity), Pursuit (accepting increased risk for performance gains), Reduction (mitigation controls), and Sharing (transferring via insurance or hedging).
Example: A company buys property insurance to share fire loss risk while setting up automated data backups to reduce cyber disruption severity.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
Four Views of Risk Integration
Integrates risks across four escalating levels: Risk view (event focus), Risk category view (operating structure focus), Risk profile view (linked to specific objectives), and Portfolio view (full top-level entity integration).
Example: Internal audit evaluates whether management progressed from isolated risk category views to a fully integrated portfolio view of risk.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
Review and Revision Component Principles
Ensures the organization continually improves ERM practices through three principles: identifying substantial internal or external context changes, reviewing performance deviations against risk tolerances, and pursuing continuous ERM enhancement.
Example: Auditors verify that management conducted a post-implementation review after a strategic expansion missed revenue targets.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
What are the inherent limitations of ERM?
Enterprise risk management cannot provide absolute assurance due to limitations arising from faulty human judgment, cost-benefit trade-offs, simple errors, employee collusion, and management override of risk practices.
Example: An internal auditor notes that automated risk controls were bypassed because executive leadership executed an unauthorized override.
Source: Subunit 7.3 COSO Framework -- ERM Components and Limitations
What is the ISO 31000 Risk Management Standard?
ISO 31000 is a globally recognized, principles-based framework that provides broad, flexible guidelines to help organizations integrate risk management into governance, decision-making, and strategic planning across all operational areas.
Example: An international corporation adopts ISO 31000 to establish a flexible, standardized risk management language across global subsidiaries.
Source: Subunit 7.4 ISO 31000 Risk Management Framework
Comparing ISO 31000 and COSO ERM Frameworks
ISO 31000 is an adaptable, principles-based framework applicable to any sector, whereas COSO ERM offers a more detailed, prescriptive structure focused closely on strategy alignment and performance.
Example: An auditor explains to the board that ISO 31000 emphasizes broad organizational integration while COSO ERM focuses on structured strategy alignment.
Source: Subunit 7.4 ISO 31000 Risk Management Framework
The 8 Core Principles of ISO 31000
ISO 31000 rests on eight principles designed to create and protect value: Integrated, Structured and comprehensive, Customized, Inclusive, Dynamic, Best available information, Human and cultural factors, and Continual improvement.
Example: Auditors evaluate whether risk assessments incorporate human and cultural factors when reviewing regional branch performance.
Source: Subunit 7.4 ISO 31000 Risk Management Framework
Board and Management Responsibilities in ISO 31000
Under ISO 31000, the board demonstrates leadership by committing resources, assigning authority, and adopting risk policies, while management establishes the organization's risk attitude and executes day-to-day risk management activities.
Example: The board allocates budget for enterprise risk software while management defines operational risk attitude parameters for trading desks.
Source: Subunit 7.4 ISO 31000 Risk Management Framework
Scope, Context, and Criteria in the ISO 31000 Process
Customizing the risk management process by defining operational boundaries, evaluating internal and external environmental contexts, and establishing risk criteria to determine unacceptable risk levels.
Example: An audit team evaluates whether management established clear risk criteria before scoring regulatory compliance risks.
Source: Subunit 7.4 ISO 31000 Risk Management Framework
Risk Assessment Steps in ISO 31000
Risk assessment in ISO 31000 consists of three distinct phases: Risk Identification (finding potential events), Risk Analysis (examining characteristics, likelihood, and severity), and Risk Evaluation (comparing results against criteria to guide action).
Example: Internal audit verifies that risk evaluation findings were directly compared against predefined risk criteria before selecting treatments.
Source: Subunit 7.4 ISO 31000 Risk Management Framework
Risk Treatment and Monitoring in ISO 31000
Risk treatment is an iterative process of selecting and implementing risk options, assessing residual risk acceptability, and adjusting treatments as necessary, supported by continuous monitoring and reporting across all phases.
Example: Management tests a newly implemented IT backup system and modifies its risk treatment plan after discovering recovery delays.
Source: Subunit 7.4 ISO 31000 Risk Management Framework
Three Assurance Approaches for Risk Management under ISO 31000
Internal audit provides assurance on the risk management process using three distinct approaches: the Key Principles approach, the Process Element approach, and the Maturity Model approach.
Example: The CAE selects the Maturity Model approach to evaluate how the enterprise risk management function progresses along its development curve over time.
Source: Subunit 7.4 ISO 31000 Risk Management Framework
All P1 chapters
- 1. Foundations of Internal Auditing
- 2. Assurance Services I
- 3. Assurance Services II
- 4. Advisory Services
- 5. Ethics and Professionalism
- 6. Governance
- 7. Risk Management
- 8. Controls: Types
- 9. Controls: Application
- 10. Fraud Risks
Choosing a qualification? CIA vs CMA 2026